Independent consultancy service
for the planning, design, auditing and site management

Client:  Taylor Woodrow International Ltd.

Preparation of tender submission method statements, drawings and quantities for a self launching gantry to erect the 552.5m long 13 span pre-cast segmental bridge.  Segments weighing up to 90Te were supported on an under slung truss system then glued and stressed together span by span.

Client:  Taylor Woodrow International Ltd.

Preparation of tender submission method statements, drawings and quantities for a self launching gantry to erect the 552.5m long 13 span pre-cast segmental bridge.  Segments weighing up to 90Te were supported on an under slung truss system then glued and stressed together span by span.